Key Points:
• Sandy Springs residents whose properties back up to SR 400 are requesting tree planting and wooden fences as between the ongoing highway widening and their homes.
• The 16-mile, $11 billion dollar expressway project is scheduled to continue through at least 2031. The Georgia Department of Transportation inked a public partnership with SR 400 Peach Partners to construct and manage the express lanes for the next half century.
• The project design is not yet finalized, but GDOT and Peach Partners have not yet committed to enhanced landscaping or fencing between Huntingdon Trail and SR 400.
With heavy construction underway along State Route 400 in north Sandy Springs, residents bordering a section of the project want to know what will replace a 10-acre forest behind their homes.
Kelly Ellis and Molly Peek, two residents whose homes along Huntingdon Trail back up to a construction zone (Exit 6) at Northridge Road, said some of their neighbors are renting out their homes, and others have been unable to sell.

Ellis said she and a couple of affected homeowners are requesting that the state and its contractor plant trees along the highway buffer and scrap a proposed chain-link fence along their property lines and around the detention pond.
“Huntingdon neighbors requested visual and noise abatement, including a more visually appealing fence, specifically a wooden fence, and noise abatement,
including trees and earthen berms,” she said.
Huntingdon homeowners
According to the neighbors, the state’s noise study for Northridge Forest showed
that “the modeled increased decibel level post-project did not warrant sound abatement.” If the criteria for noise abatement measures (which do not include trees) are not met, the state and its contractor are not obligated to take action.
“The bare ground will be covered with grass seed,” Ellis said. “There are no current plans for other vegetation to be planted or for noise barriers behind the first eight homes on Huntingdon Trail that are most affected.”
Ellis, Peek, and their group of homeowners are requesting a construction timeline and a landscape plan from SR 400 Peach Partners. They also want their local Sandy Springs City Council representative, John Paulson, to follow up with the contractor.

Paulson, who lives in the Northridge Forest neighborhood, said the highway widening project is uniquely affecting homeowners in Sandy Springs. Further north along the SR 400 corridor, most of the surrounding land is commercially zoned, with very few residential property owners.
Highway widening underway
Because of the state’s design-build contract with SR 400 Peach Partners, Paulson said it is his understanding that the builder has leeway in designing the freeway including exits like the one at Northridge Road. That created what he called a disconnect between what neighbors see in their backyards and the concept plans that they were shown to them by the state DOT years ago.
“I’m optimistic that as the project nears completion, some of the concerns the neighbors have can be addressed by the various parties involved, including DOT, the contractor, and possibly the city,” Paulson said. “[The neighbors] believed at the time that the DOT had committed these things to them, but the contractor has no obligation.”
The $11 billion express lanes project has been in the works for years. The Georgia Department of Transportation signed a public-private partnership with Peach Partners, a consortium of domestic and international engineering and construction firms.
Work is expected to last until at least 2031. The construction contractor has a 56-year, $4.6 billion contract to design, build, operate, and maintain the 16 miles of highway from the Sandy Springs MARTA station to southern Forsyth County.
So far, crews have closed the existing southbound lanes at Exit 5 and built temporary exits to the northernmost MARTA station, Abernathy Road and Hammond Drive. Tree clearing resumed in August, with significant lane restriping, earthwork, and drainage improvements.

Construction woes
Huntingdon Trail neighbors are planning to install fencing and landscaping on their private property before the project’s completion, including trees.
Ellis and Peek said they were totally unaware of a detention pond between an exit ramp and some affected homeowners further north along their street, as well as a parking lot for construction vehicles.
Except for a small, heavily wooded area near the Mayor Eva Cohn Galambos Memorial Interchange, the dense North Georgia forest and elevated terrain separating the neighborhood from the highway have been transformed.
Peek said she can see cars’ headlights at night, hundreds of yards away from their back porch on the west side of the state route.

Because of stormwater runoff from SR 400 over the past 40 years, Northridge Forest residents who live next to some small lakes in the neighborhood have worked with GDOT to remove silt. As part of the widening project, the state worked with the contractor to address that problem.
State responds
GDOT spokesperson Joe Schulman, communications manager for public-private partnerships (P3), said work on the detention pond is ongoing, along with earthwork and utility relocations. Relocation of the main waterline is anticipated to begin early next year.
“Construction schedules are subject to change,” Schulman wrote. “The project team will continue providing updates regarding upcoming activities and anticipated construction milestones.”
When asked about the future of the right-of-way between the highway exit and the neighborhood, Schulman said there are no plans to provide additional landscaping or replace trees removed for construction.
“Near the completion of construction, remaining areas within the State ROW will be seeded with grass and monitored through establishment, consistent with standard Georgia DOT practices,” Schulman wrote in an email to Rough Draft. “SR 400 Peach Partners is responsible for operating and maintaining the express lanes corridor for the duration of the project and for the next 50+ years.”
The final approval of the project design later this year will finalize the appearance of areas adjacent to residential properties, according to Schulman.
“Local municipal ordinances do not supersede the state’s authority within the state ROW,” he wrote. “However, the project will include all required erosion control measures, permanent stabilization, landscaping, and fencing elements identified in the approved design.”